H&H provided EPC services in collaboration with First Solar. 2448 (107.5 watt) modules (263 kW-DC) are installed on Rockwell campus open green space. This array is the only US installation of First Solar modules not designed and installed by First Solar. Two Ingeteam Power 125TL central inverters were used with 8 solarBOS disconnecting combiners. Schletter FS-Duo racking supports and eight-high configuration. 192 driven pile piers were installed in two days by three crew members. Project coordination with a campus-wide parking lot replacement allow for cost savings for building transformer interconnections. Local zoning height requirements, Rockwell aesthetic conditions, and grand deadlines presented some challenges, but the results speak for themselves. H&H was able to complete this project in 3 weeks.