• Solar Rooftop Installation
  • Solar Rooftop Installation
  • Oak Creek, WI

Target Stores

This project consisted of (17) 270 380kWDC rooftop arrays on Target stores in Southern Wisconsin, for a total of 5,863kWDC installed. Our contract was with the developer of the project, Greenskies Renewable Energy. All the projects are installed on flat roofs, with a ballasted racking system and minimal penetrations. The crews of H&H Solar and H&H Electric deployed anywhere between 15 to 28 field staff working in 4 different crews – Prefabricating, building, wiring, testing, and commissioning. H&H Solar was directly involved in the interconnection applications, and permitting process for each site.

Engineering

H&H Solar

Construction

H&H Electric and H&H Solar Energy Services

Market

Commercial, Retail